Pole Barn Materials Calculator
A 40 x 64 ft pole barn with 12 ft eaves, posts every 8 ft and trusses every 4 ft takes about 26 posts 17 ft long, 17 trusses, 1,716 ft of purlins, 44 roof panels and roughly 5,003 screws — about 5,685 sq ft of steel in all.
Results
Main materials
26 posts · 17 trusses
40 x 64 x 12 ft · 2,922 sq ft of roof steel, 2,763 sq ft of wall steel
- Posts
- 26
- 17 ft long (incl. 4 ft in ground)
- Trusses
- 17
- 40 ft span, 4:12
- Roof panels
- 44
- 22.1 ft long, 36 in. coverage
- Screws
- 5,003
- ~80 per 100 sq ft + 10%
A materials estimate, not a structural design. Post sizes, truss design, bracing and footers must suit your snow load, wind load and soil; use engineered trusses and follow local code.
Materials list
| Item | Quantity | Notes |
|---|---|---|
| Posts (3-ply laminated or treated) | 26 | 17 ft each |
| Concrete footers (80 lb bags) | 52 | about 2 bags per 18 in. footer |
| Trusses | 17 | 4 ft on center |
| Roof purlins (2x4 on edge) | 1,716 lin ft | 26 rows at 24 in. |
| Wall girts (2x4) | 1,248 lin ft | 6 rows at 24 in. |
| Skirt board (2x8 treated) | 208 lin ft | around the base |
| Roof steel panels | 44 | 22.1 ft long |
| Wall steel panels | 70 | 12 ft long (plus gable pieces) |
| Screws | 5,003 | #10 x 1 1/2 in. with washers |
Before you build
- Order engineered trusses designed for your local snow and wind loads, and get a building permit — many counties require one even for farm buildings.
- Set posts 4 ft deep or below the frost line on concrete footers, square the layout by measuring diagonals, and keep bays at 8 ft.
- Add trim (ridge cap, corners, eave and rake), doors and openings, and remember headers where doors interrupt girts.
- Add about 10% to lumber for waste and lay out panels so the laps face away from the prevailing wind.
Doors, windows, trim, insulation and labor are not included. Layout follows NRCS Pennsylvania Design Guide 12 defaults (8 ft posts, trusses 4 ft o.c., purlins 2 ft o.c.).
How post-frame materials are figured
The layout follows USDA NRCS Pennsylvania's prescriptive post-frame guide, built on National Frame Building Association procedures: laminated columns at most 8 ft apart, trusses 4 ft on center (or on every post with heavier purlins), purlins 2 ft apart on a 4:12 roof, wall girts about every 2 ft, posts set 4-5 ft deep on concrete footers, a treated skirt board and 29 ga steel with 36 in. coverage.
Posts = two side rows of (length / spacing + 1) plus end-wall posts. Roof steel area = 2 x rafter length (half the width plus overhang, times the pitch factor) x building length plus overhangs. Steel screws run about 80 per 100 sq ft (Fabral) — the calculator adds 10%.
Frequently asked questions
How far apart are posts on a pole barn?
Usually 8 ft, sometimes 10-12 ft with heavier headers; NRCS Pennsylvania's prescriptive design uses 8 ft maximum.
How deep should pole barn posts be?
Typically 4-5 ft on a concrete footer, and always below the frost line; soft soil needs more.
How many screws for a metal roof?
About 80 per 100 sq ft of panel (a manufacturer guideline), plus extra for trim and waste.
Sources and assumptions
This estimates materials only. Use engineered trusses, follow your local building code and snow and wind loads, and get a permit where required.